Whiteville High School Additions & Renovations

Clancy & Theys Construction Company is providing construction management services for Whiteville High School, an addition and renovation project. The new construction includes approximately 72,000 sq ft of school buildings, and the associated work was phased out into three phases.

Phase one includes the demolition of the existing fine arts music building and site preparation.  Phase two includes the construction of the new school building, structural, architectural, exterior and interior lighting, mechanical, electrical, plumbing, fire protection, roadway and parking improvements, landscaping, and site work.  Phase three includes the demolition of three existing buildings and the necessary site work.